NEPCO 580MW PEAKING POWER PLANT
LOCATION:     Wheatland, IN
CLIENT: Nepco
VALUE: $10,600,000
TRADES: Multi-trade
DATE: June 2000
       
PROJECT DESCRIPTION:
This project involved the installation of 4 - 145 MW Westinghouse 501D Gas Turbine/Generators with all supporting facilities. All 4 systems had Evaporative cooling and demin water injection to reduce emissions.
The State Group Inc. performed all civil foundation installations, all electrical work and all mechanical and piping installations on a cost reimbursable basis.
The start date on this project was mid October 1999 and was completed in June 2000.

For more information about State Group Inc. and its contracting services, please call 800.558.2034 or email us at info@stategroup.com
 
 
 
           
  ABOUT STATE
Company Profile
What Our Clients Say About State
Our Commitment to Safety
Our Commitment to Quality
Purchasing Terms & Conditions
Affiliations & Awards
News
  CAPABILITIES
Civil
Electrical
High Voltage
Mechanical
HVAC
Communications

  MARKETS WE SERVE
Automotive
Steel/Metals
Power Generation
Oil and Gas
Mining
Mission Critical Facilities
Transportation and Infrastructure
Commercial/Institutional
Power/High Voltage
     CAREERS
CONTACT
LOCATIONS
CASE STUDIES