GIBRALTAR ORE FEED UPGRADE
LOCATION:     McLeese Lake, BC
CLIENT: Taseko Mines Limited
VALUE: $3,500,000
TRADES: Multi-trade
DATE: May 2011
       
PROJECT DESCRIPTION:
Phase II of the Gibraltar Mine upgrades / expansion include modifications to allow the new SAG mill to process up to its designed capacity of 55,000 tons per day by increasing capacity in other circuits of the concentrator.
The State Group Inc. subsidiaries and affiliate companies provided the Mechanical and steel erection expertise to successfully complete the upgrade in a short period of time and were carefully coordinated with the Mine Maintenance shutdown schedules to accommodate connections to existing feed systems.
This work included installation of new underground Ore Feed Conveyor system, connection to existing ore feed circuits and erection of the Ore feed pile cover structure complete with Head house and Conveyor Gallery.

With a peak work force of approximately 120 men, work progressed on schedule. Challenging work such as lifting and setting 146’ long structural steel trusses with the 375 ton and 250 ton cranes progressed as planned as part of the erection of the Ore Feed cover structure.

For more information about State Group Inc. and its contracting services, please call 800.558.2034 or email us at info@stategroup.com
 
 
 
           
  ABOUT STATE
Company Profile
What Our Clients Say About State
Our Commitment to Safety
Our Commitment to Quality
Purchasing Terms & Conditions
Affiliations & Awards
News
  CAPABILITIES
Civil
Electrical
High Voltage
Mechanical
HVAC
Communications

  MARKETS WE SERVE
Automotive
Steel/Metals
Power Generation
Oil and Gas
Mining
Mission Critical Facilities
Transportation and Infrastructure
Commercial/Institutional
Power/High Voltage
     CAREERS
CONTACT
LOCATIONS
CASE STUDIES